AHJ Dialogue: Insights into Compliance for Energy Storage Exports in 2025 (Part II)

Author:



In our previous article, we explored the pivotal role of energy storage technologies in the global energy transition, as well as the underlying fire safety risks driving the growth trajectory of the energy storage market through 2025. As a company consistently committed to delivering cutting-edge, expert‑level services, we recognize that the energy storage sector is evolving at a rapid pace, with customers’ demand for precise, in‑depth insights steadily increasing. Accordingly, in this chapter, leveraging our professional expertise and extensive industry resources, we will provide an in‑depth analysis of the latest developments and safety‑oriented pathways shaping the energy storage industry, striving to offer clients more valuable, actionable insights and support all stakeholders in achieving steady progress within this critical field.



Question 1

What are the safety distance requirements specified in NFPA 855?

Answer

NFPA 855 does not require isolation between BESS and associated electrical equipment. Refer to NFPA 855, 2023, Section 9.5.2.6.1, which addresses clearance from exposure hazards. If transformers and inverters are connected to grid infrastructure, isolation is not required under NFPA 855.


Install the transformer in accordance with FM Data Sheet 5‑4, which specifies the required separation distances. If these separation distances cannot be met, a two-hour fire barrier may be used. The following examples illustrate how to protect critical equipment from fires originating in adjacent transformers, depending on whether the transformer is FM‑listed, whether an FM‑listed fluid is used, and the volume of that fluid.

According to NFPA 855, the minimum spacing between units is 3 feet, and large-scale fire tests will either validate or refute this standard. If the containers are well insulated and their sides remain free of openings that could expose other BESS equipment, we may observe a reduction in the number of units deployed by the few companies that have conducted such large-scale testing.



Question 2

What are the fire‑proofing requirements for energy storage system cables?

Answer

NFPA 855 (2026 edition) requires consideration of the survivability of the following safety systems: exhaust ventilation, smoke detection, fire detection, fire suppression, flammable concentration reduction systems, gas detection, and explosion control and prevention systems;


NFPA 72 defines survivability of pathways as “the ability of conductors, optical fibers, radio carriers, or other transmission systems to maintain functionality under fire conditions.”


To leverage off-the-shelf products or other viable/practical solutions and ensure the longest possible operational duration during a fire, the initial recommendations are as follows:


1) Use UL 2196‑rated cables with a 2‑hour fire‑resistance rating, or encase the cables in a 2‑hour‑or‑longer‑rated enclosure/conduit, or install the cables outdoors.


2) The control equipment shall be installed within an independent 2-hour fire-rated enclosure inside the BESS, or in a separate control cabinet/container.


3) Use exhaust fans with a high temperature rating. It is recommended to select fans whose combustible components are located outside areas that may be exposed to flames—for example, by designing the motor or seals in a way that minimizes flame exposure. This may require conducting some investigations and consulting with various manufacturers.


It should also be noted that the gas sensor itself is not designed for prolonged exposure to flame. Therefore, once a gas‑sensor signal is detected, it must be latched. This ensures that, even if the gas sensor fails, the exhaust system can continue to operate until manual reset.



Question 3

What are the requirements related to large-scale fire‑testing?

Answer

The gases released during UL 9540A testing of battery cells and modules are flammable, and at the cell‑level, the flammable gases must be ignited to assess the risk of fire spread.


For outdoor ESS installations comprising multiple cabinets, the recommended spacing between cabinets shall be determined through analysis of anticipated wind conditions and verified by large-scale fire testing in accordance with Section 9.1, and shall be reviewed by a registered professional designer to confirm that the complete combustion of one cabinet will not result in the ignition of adjacent cabinets.



The 2026 edition of NFPA 855 will include the large-scale fire‑testing standard in Appendix G, under the Guidelines for Suppression and Safety of Lithium‑Ion Battery (LIB) Energy Storage Systems (ESS).



Question 4

What are the required safety clearances between containers?

Answer

The requirements of the 2023 edition of NFPA 855 are as follows: ESSs shall be configured in modules, with each module having a maximum stored energy of 50 kWh; the minimum spacing between modules shall be 3 feet (0.9 meters). The clearance between each module and other modules or walls within the storage room or area shall not be less than 3 feet (0.9 meters). The AHJ may approve modules with larger energy capacities or reduced inter‑module spacing, provided they meet the performance criteria established in the explosion testing specified in 9.1.5.


The 2026 edition of NFPA 855 will determine minimum safety clearances based on large-scale fire testing.



Question 5

What is the actual commissioning and acceptance process for energy storage projects?

Answer

① Construction and Installation: The EPC contractor and the AHJ spend one day conducting a preliminary inspection, while the supplier and the owner’s representative allocate 1–2 days to perform Factory Acceptance Testing (FAT). Subsequently, the EPC contractor and the AHJ dedicate one day to a final on-site inspection at the installation location to verify that all mechanical work has been completed.


② Pre-commissioning: The EPC contractor, the supplier, and the owner spend 1–2 days conducting component inspections.


③ Commissioning: The vendor and the owner spend 2–6 days conducting subsystem commissioning; ITL, the vendor, and the owner devote 5–10 days to completing the on-site assessment; the public facilities agency and the owner participate in a one-day joint commissioning. Upon completion, an Operations Permit (PTO) is obtained.


④ On-site acceptance testing: The vendor and the owner spend 2–5 days conducting brief functional tests, after which final acceptance is granted and ownership is transferred.



Question 6

Backup for the fire protection system and the explosion-proof ventilation system

What are the power requirements?

Answer

NFPA 855 will standardize the concepts of EPSS (Emergency Power Standby Systems) and SEPSS (Secondary Emergency Power Standby Systems). Registered professional designers with an EPSS design background should assess duration and total load requirements and determine the specific loads of the power system.


The total load will be based on a single BESS unit operating under fault conditions, with an additional safety factor applied to account for HMA (including supporting explosions) and main‑power loss scenarios. This assessment should be supported by UL 9540A testing and large‑scale fire‑spread tests. Accordingly, customers are advised to maintain their fire‑suppression systems and explosion‑proof ventilation systems in a 24‑hour standby mode; however, the duration of alarm‑mode operation may vary depending on 9540A test data, container design, and other relevant factors.


The basic requirements for the standby power source are Class X, Type 10, Level 2 (Type 10 may be upgraded based on HMA and the transfer of critical infrastructure loads—see NFPA 110).