North American NFPA Fire Safety Regulations for Energy Storage: Interpretation (Part 4) — Large-Scale Fire Test

Author:




2026 Edition of NFPA 855 As scheduled, it will be released this year and may bring the following major changes: Large-scale energy storage systems need to undergo Larger scale The fire test.




0 1
Existing regulations pertaining to large-scale fire‑burning tests


The large-scale fire‑testing requirements for electrochemical energy storage systems in North America are not entirely new. The current version… NFPA855 at 2023 year It is explicitly stipulated that ESS systems exceeding regulatory requirements shall undergo… Large-scale fire test , provide the test report.


[ Chinese definition: With the approval of the fire safety code official, in accordance with Article 1206.2.3 Hazard mitigation analysis of the section and Large-scale fire and fire‑condition tests conducted or witnessed and reported by an approved testing laboratory. , containing more than the table 1206.2.9 The area containing a fixed battery of medium capacity shall be regarded as an ancillary use area, rather than H Group occupancy area.




0 2
Current Status of Large-Scale Fire-Testing



Testing organization

At present, the main organizations that can provide large-scale fire‑testing services are: UL , CSA , TUV Wait


Test Standard

Currently, there are no mandatory testing standards or outlines; typically, the client and the testing organization coordinate directly. Clearly defined. Commonly referenced standards / The outline has UL9540A,CSA-TS800 Wait.


Test Objective

Verify full participation ESS A fire in one unit will not spread to adjacent units or to the exterior. Help protect lives and the surrounding environment.


General Settings for Large-Scale Fire Tests
  1. Before the large-scale fire test, ESS Spacing between energy storage cabinets Wait for settings Strictly adhere to the actual station layout. (Some clients even request that the cabinet spacing be minimized to the extreme, thereby increasing the testing difficulty.)

  2. The one being tested Energy storage cabinet 100% Full‑charge load ensures that test results accurately reflect the product’s real‑world performance.

  3. During testing, the explosion vent panel remained closed.

  4. Whether or not Proactively shut down the fire protection systems of all cabinets. , depending on the client’s choice.




0 3
Why does the new edition of NFPA 855 propose larger-scale fire‑testing?

Purpose of the large-scale fire test report: It serves as a critical data source for the AHJ to assess whether the project complies with applicable codes and standards.

During North American AHJ evaluations, the focus is not on scenarios that are “possible” or “impossible,” but rather on what actions should be taken if such a scenario were to occur, in order to prevent greater loss of life and property. In other words, the AHJ seeks to understand the worst-case outcomes, and its requirements exceed those of existing testing standards, such as UL 9540A.

The 2026 edition of NFPA 855 will incorporate the large-scale fire‑burn test standard into Appendix G, which contains guidelines for the suppression and safety of lithium‑ion battery (LIB) energy storage systems (ESS). Unlike the existing large‑scale fire‑burn test, the industry also refers to it as the “even larger‑scale fire‑burn test.”

The AHJ’s requirement for a larger-scale fire test is to allow a single ESS unit to fully ignite, in order to determine whether the fire will spread to adjacent ESS units.






0 4
Larger-Scale Fire-Testing Predictions


Except for CSA-TS800 , currently UL Also writing and 2026 Edition NFPA855 The corresponding test guidelines may be included in the new version. UL9540A as reflected in the text. At present, there are differing interpretations of the “larger-scale fire‑testing” exercise; the key points are summarized as follows:


Ø   Large-scale fire validation requirements for prediction

1 , the hazards of explosions and deflagrations;

2 , the hazards of ignition and spread;

3 , explosion venting plan, ventilation and explosion protection;

4 , communication systems, fire protection systems, thermal radiation levels, surrounding exposed materials, and gas‑liquid hazards, among others.


Ø   Prediction of Assessment Content for Large-Scale Fire Tests

1 , the impact of fires and other destructive events on critical systems

2 , survivability of the communication system (time to failure)

3 , Evaluate whether the actual installation distance is appropriate.

4 , the effects of flame impingement and spread, as well as thermal runaway propagation, on surrounding exposed surfaces


Ø   Large-scale fire testing and the current version UL9540A Predicting variability

Test Objective :UL9540A It is to determine whether, after a module experiences thermal runaway, the system will generate any fires or give rise to conditions that fail to meet the required standards. UL9540A The phenomenon required by the unit. Large-scale fire‑testing is conducted in accordance with relevant guidance documents and differs from customized testing; its primary focus is to assess the worst-case scenarios that may arise when a container catches fire.

Test sample :UL9540A It can be implemented using standard shipping containers, or by integrating battery clusters directly within the containers. However, for large-scale fire‑testing, the setup must reflect the actual installation environment and container configuration; the containers need to be fully loaded, and adjacent units must be partially interconnected during installation.


Points of concern still under discussion



1
During testing, should the doors and explosion-relief panels be opened?

Judging from the AHJ’s requirement for a larger-scale fire test, it is likely that they expect the door, venting panels, and other components to fully… The chamber is opened to allow the ESS device under test to come into extensive contact with air, ensuring complete combustion. 。


2

Should passive fire protection be shut down?



The latest update is that, during large-scale fire‑testing, passive fire protection—installed in accordance with standards and compliant with fire‑safety regulations—may be activated. However, it can only be used once; once the passive fire protection system is triggered, it must be re‑ignited.

According to AHJ’s assessment framework, whether similar requirements to the TRPP system will emerge in the future is currently under discussion. In response, relevant industry bodies have also put forward recommendations:

The client may opt to conduct comparative tests—both with and without fire‑protection measures—to provide AHJs, owners, and other stakeholders with more comprehensive data. This approach not only illustrates the worst‑case scenario of complete combustion of the tested energy‑storage container under fire‑free conditions but also offers guidance on how to mitigate the hazards generated during such a fire event.





0 5
and AnDun’s large-scale fire‑burning test experimental capabilities


And An Dun with North America AHJ Moreover, leading testing organizations across the industry are joining forces to advance in-depth collaboration, poised and ready to respond before the new North American energy‑storage fire‑safety regulations take effect. Possesses large-scale fire‑testing capabilities, We can provide clients with specialized consulting on large-scale fire testing and assist in developing… Specific test plan, Equipped with facilities such as testing personnel spaces.